Why Oxfordshire is running two roadworks schemes together in Abingdon
Oxfordshire County Council normally wouldn't allow two roadworks schemes this close together, yet Abingdon has both running at once for six weeks. Here's the reasoning and what it means for drivers.
30 September 2026 | Infrastructure
By Marc Hobbins
Oxfordshire County Council says it wouldn't normally allow two roadworks schemes this close together. In Abingdon, it's doing exactly that, and it has explained why.
Two schemes, one stretch of road
From Monday 28 September, roadworks by housing developer David Wilson Homes at Abingdon's Peachcroft roundabout will run at the same time as Oxfordshire County Council's own project at the nearby A34 Lodge Hill junction. Both are set to run for around six weeks.
Where the lights will be
- Peachcroft roundabout: temporary traffic lights will manage traffic where the roundabout connects the A4183, Dunmore Road and Twelve Acre Drive.
- A34 Lodge Hill junction: two-way temporary lights will control traffic on the A4183, between the Lodge Hill garage entrance and the start of the new south roundabout.
- Timing: around six weeks, starting on Monday 28 September.
The council's own rule, and the exception
Councillor Liz Leffman, Oxfordshire County Council's Cabinet Member for Highways Construction and Repair, was upfront about the usual position. "As highways authority, we would not normally permit two schemes like this to go ahead so close to each other at the same time, due to the risk of creating additional congestion and delay."
Her case for going ahead anyway is that letting the two schemes run together "will reduce the overall duration of the disruption and avoid delays to either of these vital schemes."
The trade-off behind the overlap
The council is choosing between two imperfect options. Run the schemes one after the other and the delays stack up in sequence across a longer calendar period. Run them together and the delay compounds while they overlap, but the whole job finishes sooner.
The council has picked the second route and said so out loud, which is more than a generic roadworks warning would tell you.
Why a roundabout hates overlapping lights
Roundabouts work because traffic keeps flowing without the hard stops you get at a signal-controlled junction. Put temporary lights on one and the whole character of the place changes. Every approach becomes a controlled movement, capacity drops and the gaps disappear.
A junction that normally soaks up small surges in traffic starts storing them instead. That's the pressure building around Peachcroft right now, with a second set of signals a short distance away on the same road.
The hold-up that adds up on the A4183
If you use the A4183 every day, you'll feel the practical result. A hold at one set of lights stacks on top of a hold at the other, and a short trip can turn into something considerably longer for the full six weeks.
Our own coverage has seen a similar pattern elsewhere. In Cornwall, sat-nav rerouting around A30 roadworks sent traffic into villages never designed to carry it. Once normal traffic flow through a junction breaks, the knock-on effects spread well beyond the works themselves.
What to do before you set off
Build in significant extra time on the A4183 and around Peachcroft roundabout for the next six weeks, particularly at peak periods. Don't assume a clear run on one approach means the rest of your route will behave the same way.
You can find out more on the Oxfordshire County Council website.
This story was first featured on HighwaysIndustry.com