Banwell bypass construction area with works underway alongside the route ahead of planned water main diversions

Banwell bypass opening slips to winter 2027 over water main work

North Somerset Council now expects the Banwell bypass to open in winter 2027 instead of summer, because Bristol Water must finish moving its water mains first. Here is what has changed and why.

4 November 2026 | Infrastructure

By Marc Hobbins

Bad news for anyone counting down to summer 2027. North Somerset Council now expects the Banwell bypass to open in winter 2027, and the reason sits underground rather than on the road.

Pipes first, then the piling

Bristol Water's water main diversions have to be finished before parts of the build can start. The bypass works include ground improvements such as piling, so the water main work has to come first.

The diversions move underground services out of the Banwell bypass construction area. The aim is for water supplies to local properties to be maintained and easily reached in future.

The timetable shift in numbers

  • Previous expectation: summer 2027
  • New expectation: winter 2027
  • Traffic through Banwell village: cut by up to 78% in the opening year, the council says
  • Extra government funding: £9.7m, secured in March 2025

The council says it and contractor Galliford Try have rearranged programmes as far as possible to fit around the water work.

A century-long story with a delay

Council leader Mike Bell said: "Banwell bypass is a project with a 100-year history, set to finally tackle notorious traffic congestion in the narrows of Banwell village. Despite delay we continue to make good progress on site and the century-long wait will soon be over."

He added that the bypass will improve road links between Weston-super-Mare and the A38. The project also includes miles of new walking, cycling and horse-riding track connecting with the Strawberry Line, along with new woodland, wetland and grassland.

Contractors, funding and the road to start

Alun Griffiths Contractors Ltd pulled out in March 2024, and Galliford Try took over in September 2024. Galliford Try's contract runs in two stages, and Full Council agreed in April 2025 to go ahead with the second, main construction stage.

Milestones so far

  • 2019: Homes England funding secured
  • March 2023: planning permission granted
  • January 2024: the Secretary of State for Transport confirmed the compulsory purchase orders

The cost question still hangs over it

The release doesn't give the scheme's current cost, or whether the delay adds to it. Elsewhere, the DfT has dropped the £303m A350 Melksham bypass from its road funding programme.